Coal to methanol and convertion to olefins Zhongan project - China

After the design and manufacturing phase of the Hydroservice system, after six months Client asked Hydroservice a site supervision service on urgent basis for commissioning and start-up the unit. Hydroservice service team moved to ZhongAn China and in four days commissioned the package unit and Client could start the plant production as per schedule.

TALK TO AN EXPERT

Contact a specialist

We oversee every project from start to finish—from defining requirements to commissioning—developing tailored solutions that combine efficiency, reliability, and energy savings.

go

What Hydroservice has developed

Further to the design, engineering, manufacturing and factory acceptance test of the package system, Hydroservice provided skillful technicians for site service in rush conditions with a very tight schedule. Hydroservice co-operated with Client site team to reach the goal. The Client site team was composed of technicians from three different companies and five different disciplines (Mechanical – Instrument – Electrical – PLC Software and DCS Engineers).

The result

The result was that after four days of activities the package was positively commissioned, started-up and fully operational. The End User was able to start the production with the correct process performances in accordance with project schedule without any delay. An important project milestone has been achieved.